No Interference Possible U/S.34 A&C Act On "Excessive" Quantum Of Award Merely Because Award Debtor Is Government Entity: Supreme Court
|20 Nov 2026 7:00 PM IST
The Supreme Court was considering two appeals filed at the instance of the awarder and the contractor against the judgment under Section 37 of the Arbitration and Conciliation Act, 1996,
While restoring an arbitral award, the Supreme Court has held that no interference is possible under Section 34 of the Arbitration & Conciliation Act on the quantum of the award, which appears excessive, merely because the award debtor is a government entity.
The Apex Court was considering two appeals filed at the instance of the awarder and the contractor against the judgment under Section 37 of the Arbitration and Conciliation Act, 1996, overturning the judgment under Section 34, which affirmed the arbitration award and modified the award, quantifying the amounts payable by the awarder to 50% of that quantified by the Arbitrator and reduced the interest to 6% on the principal sum.
The Bench comprising Justice J. B. Pardiwala and Justice K. Vinod Chandran held, “The impugned judgment also expressed shock by reason merely of the enormity of the quantification for additional works exceeding 70% of the original contract for reason of the awarder being a State entity required the parties to an arbitration to be treated with equality; without any special treatment being given to the Government entity while even considering the application for grant of stay of a money decree in proceedings under Section 34 of the Arbitration Act. There can hence be no interference caused to the quantum of claim decided by the Arbitrator, based on valid material, merely for the reason that the award debtor is a Government entity and that the quantum appears to be excessive without any substantiation for such a ground being raised against the award itself.”
Arguments
It was the case of the contractor that the original contract itself was for dredging of the riverbed and shores at Sagar Island to make a channel and basin, which was put in use from April 17, 2001, when it was inaugurated by the Chairman of the awarder, Port Trust of Calcutta. Reference was made to a letter issued by the Port Trust, entrusting additional work which occurred due to 100% siltation, requiring dredging of the area repeatedly, more by reason of the Port Trust having not provided correct data of the soil constitution and having failed to construct protective walls. It was argued that the Court, under Section 37, had limited powers of interference.
The respondent Awarder Port Trust, in tune with its decision to file an appeal against the impugned judgment, sought to set aside the entire arbitral award. It was prayed that, if at all, the additional work was found to have been carried out by the contractor, then the impugned judgment had to be sustained at 50% with reduced interest of 6%.
Reasoning
The Bench referred to the judgment of the Single Judge under Section 34 of the Act, which was founded on the application praying for setting aside of the award for dredging/evacuation of the approach channel and basin project of shore-based pilot station at Sagar Island. The Bench noted that the Single Judge found that admittedly the work was completed by April 17, 2001 when the Chairman of the Port Trust inaugurated the pilot station using the channel dredged by the appellant. “That there was additional work required to be done is also evident from the letter dated 19.07.2000, addressed by the Port Trust to the contractor, produced as Annexure A35 along with the application to file additional documents. The learned Single Judge affirmed the award”, it added.
The Bench was of the view that the modification of the award merely for the reason of the Court’s conscience having been shocked also for the sole ground of the amount claimed for the additional work having exceeded 70% of the original contract, could not be sustained.
The Bench noted that the reliance placed on the documents produced by the contractor to substantiate the work carried out was found to be quite valid even in the context of the absence of a completion certificate issued under the GCC. “Having found that the arbitration award was based on adequate evidence and by no stretch of imagination it can be termed as perverse or patently illegal, we find the modification on the ground of ‘shocking the conscience’ to be not coming within the contours of the jurisdiction conferred under Section 37 and it cannot at all the be said to be in conflict with the basic notions of morality or justice”, it added.
The Bench noted that there was no question of severance of the award into separate silos since the quantification was made in accordance with valid measurements and the invoices raised by the contractor. The Apex Court found that the Division Bench, considering the application under Section 37 had not looked into the measurement or the invoices, which would have been an exercise of adjudication on merits, clearly prohibited under the Act of 1996.
According to the Bench, there could be no interference caused to the quantum of claim decided by the Arbitrator, based on valid material, merely for the reason that the award debtor was a Government entity. The Bench thus concluded that the reasoning of the Division Bench under Section 37 was not in consonance with the grounds provided under the Act.
Decision
Thus, allowing the appeal of the contractor, the Bench set aside the impugned order and restored the arbitral award.
Cause Title: M/s Marino Dredgeco Limited v. The Board of Trustees of the Port of Kolkata (Neutral Citation: 2026 INSC 1238)