Justice Somasekhar Sundaresan, Bombay High Court 

The Bombay High Court has set aside a partial arbitral award of Rs. 32.79 crores, clarifying that claims for compensation under Section 56 of the Indian Contract Act, 1872 (ICA) cannot be adjudicated summarily. The Court held that an arbitral tribunal cannot award damages for contract impossibility without actively testing the specific statutory ingredients of the provision and requiring the parties to lead empirical evidence.

Furthermore, it held that whether expenditure incurred by one party under a void contract constitutes an "advantage" gained by the other within the meaning of Section 65 is a triable question of fact requiring contractual analysis and evidence, not a conclusion assumable from the mere fact of payment, and that an admission of expenses incurred cannot be equated with an admission of advantage gained.

Justice Somasekhar Sundaresan observed, Therefore, necessarily, to invoke Section 56, the promise in question ought to have been spelt out. Then the knowledge of the promisor that the promise was an impossibility, and the absence of knowledge of the promisee about the impossibility must be shown. It is then that a case for compensation would be made out. Moreover, the very fact that Section 56 of the Contract Act provides for compensation for any loss sustained, there would be a need to assess the loss sustained and a fair assessment of how to compensate for such loss. In my judgement, the aforesaid standard would necessitate examining evidence and assessing what the parties contracted and what the promisor knew about the impossibility or illegality of performance and what the promisee did not know about such impossibility or illegality. Likewise, evidence of loss suffered would need to be led and the compensation amount would have to be arrived at based on empirical evidence. Section 56 of the Contract Act, therefore, in my opinion does not lend itself to a summary judgement in the facts of this case”.

Advocate Sanjay Jain appeared for the petitioner and Advocate Ashishchandra Rao appeared for the respondent.

As per the facts, Mahaguj Collieries Limited, a 60:40 joint venture between Maharashtra State Power Generation Company and Gujarat State Electricity Corporation, had been allotted the Machhakata coal block in Odisha. It appointed Adani Enterprises Limited as Mine Developer-cum-Operator under a Coal Mining Services Agreement dated May 2010.

The Supreme Court, through its landmark judgment of August 2014, cancelled allocation of over 200 coal blocks including Mahaguj's. Adani thereafter invoked arbitration claiming reimbursement of expenses incurred under the CMSA, primarily towards land acquisition.

The Arbitral Tribunal passed a partial award under Section 31(6) of the Act treating a letter written by Mahaguj to the Union Coal Ministry in November 2014, which confirmed that Adani had spent Rs. 201 crores, as an admission and directing payment of Rs. 32.79 crores by invoking Sections 56 and 65 of the Contract Act by conjoint reading.

The High Court found the award unsustainable on multiple grounds. The November 2014 Letter was at best an admission of expenses incurred, not an admission of advantage gained by Mahaguj.

“Not only is an Arbitral Tribunal the last word on interpretation of evidence, but also its interpretation of contract must not be lightly disturbed unless and until the view taken by the Arbitral tribunal in an arbitral award impugned is of a nature that would be totally untenable and not amenable to any reasonable reading thereby placing it in the realm of the perverse. In this case, no evidence was tested and no assessment of advantage gained or loss sustained or compensation payable was made. Every rupee spent towards land acquisition was simply asked to be paid over by Mahaguj to the MDO without anything further to be done..." the Bench noted further.

The CMSA explicitly placed the obligation to pay for land acquisition on the MDO, with recoupment embedded in the Coal Mining Service Fee formula, making it far from obvious that such payments constituted an advantage to Mahaguj.

“Against this backdrop, the summary judgement in the Impugned Award, without even an analysis of these provisions of the CMSA and without any evidence being led as to what was whose advantage, is inexplicable. Even Section 65 provides for restoration of an advantage or making compensation for the advantage received. Compensation would necessarily entail assessment, which would entail evidence being led. For the Impugned Award to be sustainable, the advantage being received should be writ large in such a manner that no further adjudication is necessary, warranting disposal of a Section 17 Application by way of a partial and conclusive award of the amounts spent towards land acquisition. The Impugned Award is silent on how such advantage is writ large”, the Bench further noted.

The tribunal had dismissed Mahaguj's response as "weak and unconvincing" without identifying any reason for that conclusion. The CMSA's independent contractor clauses expressly negating agency, which directly contradicted the tribunal's reasoning, were never addressed.

The award was set aside with liberty to parties to pursue arbitration afresh.

Cause Title: Mahaguj Collieries Ltd. v. Adani Enterprises Ltd. Commercial Arbitration Petition NO. 483 OF 2018

Appearances:

Petitioner: Sanjay Jain with Sneha Phene, Jayendra Kapadia, Anupreeta Bhat & Indraneel Nanoti, Advocates.

Respondent: Ashishchandra Rao, Ria Dalwani, Urja Thakkar & Aditi Rai, Advocates instructed by Economic Laws Practice.

Click here to read/download the Judgment


Tags: