Highest Bidder Has No Vested Right To Conclusion Of Contract Before Formal Acceptance: Allahabad High Court
| The Court upheld the cancellation and re-tendering but allowed the petitioner one week to accept the original L-1 rate, which the State was directed to honour in the absence of any other legal impediment.
The Allahabad High Court has held that being the highest bidder does not create a vested or indefeasible right to the award of a government contract before the competent authority finally accepts the bid and it is translated into a formal contract or agreement.
The Court said that the bidder has limited rights to equality, fair treatment and negotiation but cannot compel the State to accept its offer.
The Court was hearing a writ petition challenging the cancellation of an e-tender for transporting food grains under a single-stage doorstep-delivery system and the issuance of a fresh tender. The petitioner also sought a direction requiring the authorities to treat it as the highest bidder and issue the work order in its favour.
A Bench of Justice Prakash Padia and Justice Indrajeet Shukla observed: “So long as an order regarding final acceptance of the bid has not been passed by the competent authority, even if the petitioner is considered to be the highest bidder, does not acquire a vested right to the conclusion of the contract, particularly in view of Section 4 of the Indian Contract Act, which speaks of when communication is complete. Thus, as has been held in Om Prakash Sharma (supra). The highest bidder has limited rights of equality, fair treatment and negotiation; the bid offered by him cannot be enforced unless the same is translated into a formal contact, /agreement.”
Advocate Rajeev Kumar Singh appeared for the petitioner. Additional Chief Standing Counsel Dharmendra Prasad Singh appeared for the State respondents.
Background
The Court noted that three bidders submitted technical and financial bids for the food-grain transportation work. The Tender Evaluation Committee initially found all three technical bids responsive, following which the financial bids were opened. Another bidder was declared L-1, while the petitioner was ranked L-2.
The Court noted that, after inquiring into a subsequent complaint, the authorities found that the L-1 bidder had proposed a tanker authorised to transport petroleum products rather than a vehicle suitable for carrying food grains. They consequently cancelled the work order issued to that bidder.
The Court noted that the authorities then asked the petitioner and the third bidder whether they were willing to execute the work at the rate quoted by the original L-1 bidder. Neither bidder gave the required consent, and the authorities cancelled the tender and initiated a fresh process.
The petitioner contended that the original L-1 bidder's technical bid had been ineligible from the outset and that the petitioner should therefore have been treated as L-1 at its own quoted rate. The petitioner also alleged unequal treatment by referring to another block where an L-2 bidder had received the contract after the L-1 bidder was disqualified.
The State submitted that the petitioner had been offered negotiation at the original L-1 rate but had declined to consent. It maintained that cancellation and re-tendering protected public interest and government revenue and that the comparison with the other block ignored material factual differences.
Court's Observations
Highest Bidder Could Not Compel Acceptance Of Its Rate
The Court held that no bidder could compel the State to accept its quoted rate before a formal contract came into existence. It found that even if the petitioner was treated as the effective L-1 bidder after the disqualification, its status did not create an enforceable right to the work order.
The Court relied on U.P. Avas Evam Vikas Parishad v. Om Prakash Sharma (2013), which had held that a highest bidder acquires no vested right in the absence of acceptance by the competent authority.
The Supreme Court had further explained in Meerut Development Authority, as reproduced in Om Prakash Sharma: “The Authority has the right not to accept the highest bid and even to prefer a tender other than the highest bidder, if there exist good and sufficient reasons, such as, the highest bid not representing the market price but there cannot be any doubt that the Authority's action in accepting or refusing the bid must be free from arbitrariness or favouritism.”
Tender Decisions Remained Subject To Article 14
The Court clarified that the contractual character of a transaction did not give the State unfettered discretion. It held that government tender decisions remained reviewable for arbitrariness, irrationality, discrimination, perversity or mala fides, although constitutional courts ordinarily exercised restraint in commercial matters.
The Court referred to Save Mon Region Federation v. State of Arunachal Pradesh (2026), in which the Supreme Court had observed: “Public interest is the paramount consideration. One of the ordinary and safest methods of securing that public interest is by inviting competition through tenders. A departure from competitive tendering may be permissible in a limited set of situations, but only when the departure is justified by rational and recorded reasons that do not suggest discrimination.”
The Court found no mala fides in the present case. It held that the petitioner had received an opportunity to negotiate at the original L-1 rate but had not accepted it at the relevant stage.
Cancellation And Re-Tendering Were Justified
The Court found that the authorities acted in accordance with the procurement manual after neither remaining bidder consented to execute the work at the original L-1 rate. It accepted the State's explanation that cancellation and re-tendering were undertaken in the interests of the Government and the public.
The Court rejected the petitioner's claim of parity with the tender for another block. It found that the L-2 bidder in that process had accepted the L-1 rate and later agreed to the government-prescribed rate, whereas the petitioner had declined the corresponding proposal.
The Court further held that the serial numbers in the cancellation and fresh-tender letters had been inadvertently interchanged. It found that both decisions had been taken on the same day and that the clerical error did not invalidate the process.
Although the Court found that the clerical error did not assist the petitioner, it cautioned: “Though, the tender process requires fairness particularly when State is one of the parties, thus, the State Authorities are cautioned to be careful in future.”
Petitioner Permitted To Accept Original L-1 Rate
During the hearing, the petitioner expressed willingness to execute the contract at the original L-1 rate. The State stated on instructions that it had no objection and that the voluntary consent would be honoured.
The Court directed: “Thus, we permit the petitioner to file a fresh representation according his consent and willingness for execution of work at rate L-1 as offered by M/s Hamara Pump, and if such offer is made within a period of one week from today, the same shall be honoured by the State authorities and the work order shall be executed accordingly with all promptitude, if there is no other legal impediment.”
Conclusion
The High Court held that the petitioner had no indefeasible right to the contract merely because it could be treated as the highest bidder after the original L-1 bidder's disqualification. It upheld the cancellation and fresh tender process but permitted the petitioner to submit, within one week, its consent to work at the original L-1 rate.
The Court directed the State to honour such an offer promptly if no other legal impediment existed. The Court disposed of the writ petition and made no adverse costs order.
Cause Title: M/s Shiv Anant Enterprises v. State of U.P. and 3 Others (Neutral Citation: 2026:AHC:237675-DB)